Reactor allows to switch the current project easily using a button.

In the Project Manager, open the project details for the project you want to switch to. Copy the project's Filename exactly. It is necessary to toggle on Show Advanced to see the file name. 

Screenshot 2023-11-08 at 1.54.39 PM.png


On the Configuration Page, select the button to configure. In the Inspector, select Choose other Parameter under the System options. 

Screenshot 2023-11-08 at 2.06.13 PM.png

In the dialog box that pops up select:  Reactor/CurrentProject  then Submit

projectswitch ioref.png

Returning to the Inspector, select Show More if you do not see Settings Template available. 

Screenshot 2023-11-08 at 2.06.58 PM.png

In the Settings Template, select Set Value Directly:

Screenshot 2023-11-08 at 2.07.21 PM.png

This should then give you the option to define the value needed. 

The first box will contain the Project File Name as directly copied from the Project Details. The second box can contain any name you would like to be displayed on the hardware panel.

Screenshot 2023-11-08 at 2.08.03 PM.png

 

You should end up with a button like this:

Screenshot 2023-11-08 at 2.25.37 PM.png

Please Note, changing the current project will disconnect controllers if they are not configured in the project that is being switched to. 

Make sure to configure the projects to be switched between in each project.